TEAMER Post-Access Requirements

TSRs are required to complete (within 60 days of the completion of activity at the TEAMER Facility) a series of post access requirements, including, but not limited to:

  • Completion of a Post Access Report, which must be reviewed and approved by the TEAMER Facility and TEAMER Technical Board;
  • Uploading to the TEAMER DOE Marine and Hydrokinetic Data Repository at: https://mhkdr.openei.org (“MHK-DR”) (a) data demonstrating progress towards meeting the objectives identified in Sections 6 & 8 of the TSR application (Project Summary & Assistance Data), and (b) scripts and data used to generate all figures, tables, and charts in the final report to the MHK-DR. TSRs are advised that artificially limiting the number of figures in the final report (to avoid disclosing underlying data) will be considered non-compliance with final reporting requirements and will not be approved;
  • Review and approval of all Post Access Reports by the TEAMER Facility and TEAMER Technical Board; and
  • Completion of a post access questionnaire about the TSR’s TEAMER Program experience.

How to Use this Test Plan & Post Access Report Template

This document provides a template for both the Test Plan and the Post Access Report. Instructions on how to use this template are as follows:

  • When developing the Test Plan, please complete Sections 1-6 of the template. Sections 7-10 can be removed. Please add Appendices as needed.
  • When developing the Post Access Report, please complete all sections of this template. Sections 1-6 should be based on the Test Plan that was submitted. For the Post Access Report, Sections 1-6 must be updated to reflect where actual work deviated from the Test Plan, or where additional information is needed to describe the work actually performed during testing. Any changes to Sections 1-6 in the Post Access Report must be indicated using track changes for Version 2 described below.
  • The Executive Summary section of the template should only be completed for the Post Access Report and does not need to be completed for the Test Plan
  • Mark all items that are considered intellectual property (IP) in the document by highlighting in yellow. IP highlighting will be reviewed to ensure consistency with the IP agreement established with the TEAMER Network Director.
  • Provide two (2) versions of the finalized Post Access Report. Version 1 should include information for immediate public viewing with protected data redacted or excluded. Version 2 must include all protected data as stated by the data requirement guidelines for the award.

Notes on guiding text provided throughout this template:

  • Black text defines the structure for the Test Plan and Post Access Report. Black text should not be removed or modified without approval from the TEAMER Network Director.

3 Project Objectives

4 Test Facility, Equipment, Software, and Technical Expertise

5 Test or Analysis Article Description

6 Work Plan

This section should provide a high level description of the research methods. Regardless of the type of support being provided, this section should include sufficient detail, within reason, to allow the methods to be duplicated and for all results to be understood and interpreted.

6.1 Experimental Setup, Data Acquisition System, and Instrumentation (For Experimental Projects Only, Numerical Projects Please Delete this Section)
6.2 Numerical Model Description
6.3 Test and Analysis Matrix and Schedule
6.4 Safety
6.5 Contingency Plans
6.6 Data Management, Processing, and Analysis
6.6.1 Data Management
6.6.2 Data Processing
6.6.3 Data Analysis

7 Project Outcomes (Required for Post Access Report Only)

7.1 Results
7.2 Lesson Learned and Test Plan Deviation

8 Conclusions and Recommendations

9 References

10 Acknowledgements
11 Appendix